Here is the 1st 3 weeks work schedule!
Week Job
1 Remove front bumper
1 Remove FMIC
1 remove propshaft
1 remove transfer box
1 Remove Front Driveshafts and refit for rolling shell
1 remove gearbox
1 send gearbox to Elite
1 Remove engine
1 Remove PRM engine damper
1 remove Cdi
1 Remove PU engine mounts
1 remove turbos
1 remove inner wheel arches?
2 Remove Rear Bumper
2 Remove Seats
2 Remove carpets
2 Remove EDFC Wiring
2 Remove Centre Console
2 Remove Head lining
2 Remove all interior Trims
2 Remove ABS, ECS, Cruise ECU's etc
2 Remove Air con Box and pipe work
2 Remove Heater Box
2 Remove dash, Clocks Etc
2 Remove Seat belts
2 Remove main and anciallry looms
2 Remove Fuel Tank
2 Fit Double Pump Bracket and Pumps
2 Remove All other Wiring
2 Remove Shifter/Cables
2 remove all relay and fuse boxes
3 Remove Front Sub Frame and refit
3 Remove Rear Sub Frame and refit
3 Remove ABS Pump, wiring and pipes
3 Fit MR Brake Lines and Compensator Valve
3 Perform Rear steer delete
3 Remove Rear Diff and refit
3 Plug rear diff pump hole
3 Remove rear steer comand lines
3 Remove rear steer supply Lines
3 Fit MR Power Steer Reservoir
3 Fit Front rack blanking plugs
3 Remove Front to rear fuel Lines
André :eek5::eek4:
I voted for all 3 ;)
Good luck. This thread is worthless without pics ;)
I'll try to get as many taken as possible, but bear in mind I am over 30 miles away from my car.Quote:
Good luck. This thread is worthless without pics
André
I can't wait to see this project finished!
subscribed
i still think you're off your rocker.
Well, we have had a little bit of time slippage to the project mainly due to a delay in the roll cage arriving on time. In the end, the guy I bought it from saved the day by getting it freight shipped from his work and without his help, we would be even further behind now.
The car is pretty much totally stripped and the cage has been loosely fitted but we need to weld a plate on underneath the drivers foot well and underseal.
So the jobs for next week are:
- weld in plate
final fitting of roll cage
fit dash
relocate pillar mounted gauges
relocate defi link meter
relocate EDFC
Strip the heads and send off for measuring
refit centre console
Strip stroker short block and reassemble with new clutch
Build new main loom
Although there was a month of slack built into the project, we need to make up the couple of weeks we have lost to preserve that 1 month buffer for the unforeseen stuff.
This is where we are parts wise.
Parts required got? ordered?
Phase 1
Dual Pump Hanger y y
front to back brake lines n y
fuel pump y y
300m driveshafts y y
Phase 2
roll cage y y
mk1 dash y y
collars for roll cage n n
AIM MXL y y
Fuel return line y y
Phase 3
Stroker block y y
DR1400 kit y y
Phase 4
Billet oil gears y y
Lifters n n
Phase 5
Carbonetic clutch y y
90mm plenum y y
gearbox y y
solid mounts y y
rad fans y y
spray bar n y
fmic y y
2nd oil cooler n n
90mm throttle body y y
twin intake y y
water meth tank n n
Phase 6
afr gauge n y
fit Racelogic Vbox n y
Phase 7
transfer box y y
shifter kit n y
seats y y
seat subframes y y
harnesses y y
18x10.5 wheels n y
17x9 wheels n y
R888 315/30/18 tyres y y
MT ET Street tyres n y
splitter n y
Sorry about the table alignment
André
Updates woohoo!!!!!!!!
I want to see the finished product!
:love3:
I wish I could forget this thread existed and rediscover it when it was finished. :Shovel: